PJM Delays Backstop Capacity Plan After FERC Partial Approval

Oct 1
1 min read

On October 1, 2026, PJM Interconnection, L.L.C. (“PJM”), announced it would be delaying its reliability backstop procurement auction plan in response to the Federal Energy Regulatory Commission’s (“FERC”) September 29, 2026, decision on the plan. Although FERC accepted the plan in part, FERC had several criticisms and delayed the auction until February 28, 2027.


PJM’s plan, filed on July 31, 2026, was proposed to make up for the 6.8 GW shortfall that resulted from PJM’s 2028-2029 capacity auction. In its decision, FERC acknowledged the severity of the issue, but said that PJM’s plan fell short, and that the agency was not given enough time to properly review the plan. PJM has not yet provided a specific timeline for their new plan, but says that they will “… work quickly to address the commission’s remaining concerns.”

 

FERC’s decision is available for download from their eLibrary: https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260929-3099

Comments


Commenting on this post isn't available anymore. Contact the site owner for more info.

© 2026 by The Law Office of John Ratnaswamy, LLC

10 S. Riverside Plaza, Suite 875, Chicago, Illinois 60606

The Supreme Court of Illinois does not recognize certifications of specialties in the practice of law and certificates, awards, and recognitions are not a requirement to practice law in Illinois.