top of page

FERC Enacts Landmark Transmission Planning Rule – Order No. 1920

On May 13th 2024, the Federal Energy Regulatory Commission (FERC) enacted a new rule regulating the long-term planning of regional transmission facilities: “Order No. 1920”.


The new rule has been characterized as a “landmark” by many stakeholders.


FERC’s press release about Order No. 1920 states in part:


FERC acted today to ensure the transmission grid can meet the nation’s growing demand for reliable electricity with a new rule that outlines how to plan and pay for facilities that regions of the country will need to keep the lights on and power the American economy through the 21st Century.


Today’s rule, Order No. 1920, marks the first time in more than a decade that FERC has addressed regional transmission policy – and the first time the Commission has ever squarely addressed the need for long-term transmission planning.


The grid rule adopts specific requirements for transmission providers to conduct long-term planning for regional transmission facilities and determine how to pay for them. It reflects tens of thousands of pages of comments, filed over the course of the past three years, from hundreds of stakeholders representing all sectors of the electric power industry, advocacy groups and state and other government entities. 


FERC’s Fact Sheet about Order No. 1920 states in part:


The grid rule contains these major elements:


·       Requirement to conduct and periodically update long-term transmission planning to anticipate future needs.

·       Requirement to consider a broad set of benefits when planning new facilities.

·       Requirement to identify opportunities to modify in-kind replacement of existing transmission facilities to increase their transfer capability, known as “right-sizing.”

·       Customers pay only for projects from which they benefit.

·       Expands states’ pivotal role throughout the process of planning, selecting, and determining how to pay for transmission facilities.


Long-Term Regional Transmission Planning


More specifically, the rule requires each transmission operator to:


·       Produce a regional transmission plan of at least 20 years to identify long-term needs and the facilities to meet them.

·       Conduct this long-term planning at least once every five years using a plausible and diverse set of at least three scenarios that incorporate specific factors and use best available data.

·       Apply seven specific benefits to determine whether any identified regional proposals will efficiently and cost-effectively address long-term transmission needs.

·       Include an evaluation process to identify long-term regional transmission facilities for potential selection in the regional plan.

·       Include a process giving states and interconnection customers the opportunity to fund all, or a portion, of the cost of a long-term regional transmission facilities that otherwise would not meet the transmission provider’s selection criteria.

·       In the event of delays or cost overruns, reevaluate long-term regional transmission facilities that previously were selected in a regional transmission plan.

·       Consider transmission facilities that address interconnection-related needs identified multiple times in existing generator interconnection processes, but that have not been built.

·       Consider the use of Grid Enhancing Technologies such as dynamic line ratings, advanced power flow control devices, advanced conductors and transmission switching.


How to Pay for Transmission


The grid rule contains these cost-allocation provisions:


·       Before applicants submit compliance filings, they must open a six-month engagement period with relevant state entities.

·       Applicants must propose a default method of cost allocation to pay for selected long-term regional transmission facilities.

·       Applicants may propose, a state agreement process that lasts for up to six months after a project is selected for participants to determine, and transmission providers to file, a cost allocation method for the selected facilities.


Enhanced Transparency, “Right-Sizing” and Interregional Transmission Coordination


The grid rule requires transmission providers to:


·       Be transparent regarding local transmission planning information and conduct stakeholder meetings during the regional transmission planning cycle about the local process.

·       Identify opportunities to modify in-kind replacement of existing transmission facilities to increase their transfer capability, known as “right-sizing,” when needed.

·       Give incumbent transmission owners a right of first refusal to develop these “right-sized” replacement facilities.

·       Revise existing interregional transmission coordination processes to reflect the new long-term regional transmission planning reforms.


Order No. 1920 takes effect 60 days after publication in the Federal Register.  Compliance filings with respect to most of the rule’s requirements are due within 10 months of the effective date, while filings to comply with the interregional transmission coordination requirements are due within 12 months of the effective date.




Commentaires


Les commentaires ont été désactivés.
bottom of page